Committee to Investigate the Causes of, and National Response to, the Island wide Power Outage in Trinidad on Wednesday February 16, 2022

TRINIDAD AND TOBAGO, March 23 - 2022 February 25th

Committee to Investigate the Causes of, and National Response to, the Island wide Power Outage in Trinidad on Wednesday February 16, 2022

(Appointed on February 22, 2022)

On Tuesday, February 22, 2022 the acting Prime Minister in fulfillment of the Government’s commitment which was given in the Parliament on Friday, February 18, 2022 issued letters of appointment to members of the Committee appointed to investigate the cause of, and national response to, the island wide power outage which took place on Wednesday, February 16, 2022.

The members of the Committee are as follows: -

Professor Chandrabhan Sharma, PhD                                 -          Chairman retired Professor of Electrical Engineering

Mr. Keith Sirju former Chairman of TTEC; and

Ag. Superintendent Allister Guevarro Trinidad and Tobago Police Service.

The terms of reference of the Committee, which were issued along with their letters of appointment, requires the Committee to investigate, make site visits, review documents and interview witnesses, stakeholders and interested parties, regarding the following:-

  1. Investigation of the incident that occurred on February 16, 2022, that led to an island-wide electrical power outage in Trinidad, including, inter alia, the following: -
    1. Investigation of the circumstances that caused fault(s) to develop on T&TEC’s lines at Gandhi Village/Union Estate and any other location;
    2. Investigation of how these fault(s) resulted/contributed to a loss of generating capacity at the Trinidad Generating Unlimited (TGU) power plant and knock-on effect at other Independent Power Producer (IPP) power plants;
    3. Determination of what, if any, measures could have been taken to mitigate the impact of these fault(s) on TGU’s generating capacity;
    4. Determination of what, if any, measures could have been taken to mitigate the loss of TGU’s generating capacity and the loss of generating capacity at the other IPP’s; and
    5. Examination of the methodology and approach utilised by TGU and all other IPP’s in re-establishing electrical power supply on the island following the complete loss of generating capacity.

 

  1. Investigation of the current design/configuration/installation of T&TEC’s electrical transmission and distribution system to determine whether there are systemic design/installation features which make it vulnerable to a repeat of a similar event, whether by accident, natural or man-made causes.

 

  1. Examination of the effectiveness and appropriateness of the communication by T&TEC, ODPM and any other state agency responsible for communication in the situation, on the nature of the problem and on the progress being made to restore electrical power to the national population

 

  1. Examination of the national security response to the event of February 16, 2022 to determine the following: -
    1. The country’s state of preparedness in response to the incident that occurred; and
    2. The country’s vulnerability to a repeat occurrence, given the current design/configuration/installation of T&TEC’s electrical transmission and distribution system and the current capability of the IPP’s to respond quickly and efficiently in a similar situation in the future.
    3. The nature of the response by the protective services, national security agencies and other relevant agencies, such as the Office for Disaster Preparedness and Management, to the power outage

 

Upon completion of their investigation, the Committee is to make observations, findings and conclusions, as well as recommendations to avoid a recurrence of a nationwide power outage and report to the Office of the Prime Minister within one (1) month of the Committee’s date of appointment, i.e. by March 22, 2022.

It should be noted that the Committee may co-opt any other expertise and resources that it requires.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.